ICGB completes Greece-Bulgaria link, receives certification

Premium Content

August 09, 2022

An exterior view of the Interconnector Greece Bulgaria natural gas pipeline. (Photo: Reuters.)

Construction on the Interconnector Greece-Bulgaria (IGB) pipeline was completed last month and its operator received a final certification, allowing it to act as an independent transmission operator. The company became the second independent transmission operator in Bulgaria.

ICGB’s CEO on the Bulgarian side, Teodora Georgieva, told media later in July that the company intended to offer interested parties all unbooked capacity on the pipeline.

The IGB pipeline has an initial capacity of 105.9 Bcf/y (3 × 109 m3/y), of which 55.4 Bcf/y (1.57 × 109 m3/y) has been secured under long-term contracts of up to 25 years. Linden Energy has also said it would use 10% of the pipeline’s capacity following its acquisition of Bulgaria’s Overgas, for which it is currently seeking regulatory approval.

The remaining capacity will be offered to all interested parties. If the market shows interest in volumes above IGB’s initial capacity, this could encourage ICGB to expedite efforts to expand the pipeline.

As of late July, there were still certain final steps that still needed to be completed before the IGB pipeline could be placed into service.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, CompressorTech² News features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Latest News
VIDEO: Caterpillar G3520K Gas Gen-set Targets Evolving Energy Needs
New model comes in three configurations with enhanced transiet response, fuel flexibility and more
Everllence technology selected for Stockholm Exergi’s large-scale BECCS project
Former MAN Energy Solutions unit to supply compressor and expander train for carbon removal facility
Wison New Energies and Siemens Energy sign MoU on floating LNG cooperation
Agreement focuses on turbine and compressor packages to streamline offshore project development
CONNECT WITH THE TEAM
Jack Burke Senior Editor Tel: +1 262 527 0815 E-mail: [email protected]
Gabriele Dinsel Brand Manager Tel: +49 711 34 06 73 50 E-mail: [email protected]
Kristin Pride USA Sales Representative Tel: +1 720 298 8546 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

WEBINAR: Carbon Capture and Storage

COMPRESSORTech² is giving you a front-row seat to the technologies making CCS work today. Join Baker Hughes and Caterpillar as they share hands-on case studies and deployment insights—from CO₂ compression and pipeline transport to secure underground storage.

📅 December 4 2025

I want to attend!