Construction on the Interconnector Greece-Bulgaria (IGB) pipeline was completed last month and its operator received a final certification, allowing it to act as an independent transmission operator. The company became the second independent transmission operator in Bulgaria.

ICGB’s CEO on the Bulgarian side, Teodora Georgieva, told media later in July that the company intended to offer interested parties all unbooked capacity on the pipeline.

The IGB pipeline has an initial capacity of 105.9 Bcf/y (3 × 109 m3/y), of which 55.4 Bcf/y (1.57 × 109 m3/y) has been secured under long-term contracts of up to 25 years. Linden Energy has also said it would use 10% of the pipeline’s capacity following its acquisition of Bulgaria’s Overgas, for which it is currently seeking regulatory approval.

The remaining capacity will be offered to all interested parties. If the market shows interest in volumes above IGB’s initial capacity, this could encourage ICGB to expedite efforts to expand the pipeline.

As of late July, there were still certain final steps that still needed to be completed before the IGB pipeline could be placed into service.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, CompressorTech² News features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Latest News
Three U.S. regions each produce more natural gas than most countries
Appalachia, Permian and Haynesville rank among the world’s largest supply sources
Pembina and Petronas sign 20-year capacity agreement for Cedar LNG
Deal supports Canadian LNG export growth and long-term supply to Asian markets
KBR to provide detailed engineering for Iraq gas growth project
Work supports associated gas processing expansion at Ratawi oil field
CONNECT WITH THE TEAM
Jack Burke Senior Editor Tel: +1 262 527 0815 E-mail: [email protected]
Kristin Pride Brand Manager – North America/European Sales Executive Tel: +1 720 298 8546 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

WEBINAR: Carbon Capture and Storage

COMPRESSORTech² is giving you a front-row seat to the technologies making CCS work today. Join industry leaders as they share hands-on case studies and deployment insights - from CO₂ compression and pipeline transport to secure underground storage.

📅 December 4 2025

I want to attend!